I’m pleased to share an update on the Network Rail Alexandra Palace Station Access for All Scheme. This is an issue that Cllr Gingell and I have campaigned on, and having chased for an update some months ago, I’m happy to see that it is now moving forward. Step-free access will make a real difference to parents with buggies, disabled passengers, the elderly and everyone else who struggles with the current arrangements.
The scheme is being delivered by Network Rail and its contractor BAM Infrastructure. It will include new lifts, walkways and associated station improvements, and the overall project is expected to continue through to early 2028.
Key works and traffic management
The main impacts on the local highway network will be:
- From 23 November 2026: a footway closure and road width reduction on Buckingham Road, adjacent to the station, to facilitate construction.
- 28 to 29 November 2026: a weekend station closure for initial construction activities.
- 24 to 27 December 2026: a full closure of Buckingham Road adjacent to the station while a scaffold bridge is installed using a crane. There will be 24-hour working during this period.
- Parking suspensions and temporary changes to local street infrastructure will also be needed during parts of the programme.
Pedestrian access to residential properties will be maintained wherever possible throughout the works.
Communications so far
Network Rail and BAM Infrastructure have advised that they have:
- Issued a resident letter in October 2026 setting out the proposed works and programme.
- Delivered a letter drop to properties near the station.
- Put up advance warning signage.
- Held a community engagement event at St Paul’s Catholic Primary School on 2 November 2026.
Many thanks to residents and stakeholders who have raised this issue and campaigned for it at various times over the years. This improvement is the result of that sustained effort.
I appreciate that works of this scale will cause some disruption, particularly the Christmas closure of Buckingham Road, and I’d ask for your patience while this important improvement is delivered. If you have any concerns or issues during the works, please get in touch and I will raise them with Network Rail and BAM Infrastructure.